— Project Summary

Queue ID
LADWP-Q62
Capacity
75 MW
Technology
Battery
Status
active
Location
Los Angeles, CA
Region
West
Developer
IA Status
System Impact Study

BetaActiveBatteryLADWPLBNL

75 MW storage in Los Angeles, CA · In queue since October 2017 · Proposed COD June 2020

75 MW

Capacity

1

Components

Battery

8y 5m

In Queue

System Impact Study

IA Status

COD target: 2020

Interconnection Timeline

Total Duration

2y 8m

Schedule

71 months past proposed COD

Impact Study25%
Queue EntryOct 3, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2020-06-01

Project Details

State

CA

County

Los Angeles

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

138kV Bus Station C Wilmington

Data Source

LBNL

No news available for this project.