BetaActiveSolarBatteryLADWPLBNL
300 MW hybrid in Kern, CA · In queue since January 2017 · Proposed COD June 2020
300 MW
Capacity
2
Components
Solar + Battery
9y 2m
In Queue
System Impact Study
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3y 5m
Schedule
70 months past proposed COD
Impact Study25%
Queue EntryJan 19, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-06-21
Technology
Solar150 MW · 50%
Battery150 MW · 50%
Project Details
State
CA
County
Kern
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Rosamond 230kV Switching Station
Data Source
LBNL
No news available for this project.