— Project Summary

Queue ID
LADWP-Q53
Capacity
570 MW
Technology
Solar+Battery
Status
active
Location
Millard, UT
Region
West
Developer
Intermountain Power Agency
IA Status
IA Pending

BetaActiveSolarBatteryLADWPLBNL

570 MW hybrid in Millard, UT · In queue since July 2016 · Proposed COD June 2019

570 MW

Capacity

2

Components

Solar + Battery

9y 8m

In Queue

IA Pending

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

2y 11m

Schedule

82 months past proposed COD

In Study38%
Queue EntryJul 28, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-06-30

Technology
Solar285 MW · 50%
Battery285 MW · 50%
Project Details

State

UT

County

Millard

Region

West

Developer

Intermountain Power Agency

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

IPP 345kV Switchyard

Data Source

LBNL