800 MW hybrid in Millard, UT · In queue since January 2016 · Proposed COD January 2021
800 MW
Capacity
2
Components
Solar + Battery
10y 2m
In Queue
Operational
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
5 years
Schedule
63 months past proposed COD
Pre-Study100%
Queue EntryJan 5, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-01-30
Technology
Solar400 MW · 50%
Battery400 MW · 50%
Project Details
State
UT
County
Millard
Region
West
Developer
Intermountain Power Agency
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
IPP 345kV Switchyard
Data Source
LBNL