BetaActiveSolarBatteryLADWPLBNL
600 MW hybrid in Millard, UT · In queue since August 2015 · Proposed COD January 2020
600 MW
Capacity
2
Components
Solar + Battery
10y 7m
In Queue
Operational
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
4y 5m
Schedule
75 months past proposed COD
Pre-Study100%
Queue EntryAug 25, 2015
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-01-30
Technology
Solar300 MW · 50%
Battery300 MW · 50%
Project Details
State
UT
County
Millard
Region
West
Developer
Intermountain Power Agency
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
IPP 345kV Switchyard
Data Source
LBNL
No news available for this project.