BetaActiveSolarBatteryLADWPLBNL
600 MW hybrid in Clark, NV · In queue since December 2013 · Proposed COD September 2014
600 MW
Capacity
2
Components
Solar + Battery
12y 3m
In Queue
System Impact Study
IA Status
COD target: 2014
Interconnection Timeline
Total Duration
9 months
Schedule
140 months past proposed COD
Impact Study25%
Queue EntryDec 4, 2013
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2014-09-30
Technology
Solar300 MW · 50%
Battery300 MW · 50%
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Marketplace 500kV
Data Source
LBNL
No news available for this project.