— Project Summary

Queue ID
LADWP-Q45
Capacity
600 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryLADWPLBNL

600 MW hybrid in Clark, NV · In queue since December 2013 · Proposed COD September 2014

600 MW

Capacity

2

Components

Solar + Battery

12y 3m

In Queue

System Impact Study

IA Status

COD target: 2014

Interconnection Timeline

Total Duration

9 months

Schedule

140 months past proposed COD

Impact Study25%
Queue EntryDec 4, 2013

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-09-30

Technology
Solar300 MW · 50%
Battery300 MW · 50%
Project Details

State

NV

County

Clark

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Marketplace 500kV

Data Source

LBNL