BetaActiveSolarBatteryLADWPLBNL
200 MW hybrid in Clark, NV · In queue since November 2012 · Proposed COD April 2015
200 MW
Capacity
2
Components
Solar + Battery
13y 4m
In Queue
Facility Study
IA Status
COD target: 2015
Interconnection Timeline
Total Duration
2y 5m
Schedule
133 months past proposed COD
Facilities Study50%
Queue EntryNov 28, 2012
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2015-04-30
Technology
Solar100 MW · 50%
Battery100 MW · 50%
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Marketplace Substation
Data Source
LBNL
No news available for this project.