— Project Summary

Queue ID
LADWP-Q30
Capacity
170 MW
Technology
Solar+Battery
Status
suspended
Location
Kern, CA
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryLADWPLBNL

170 MW hybrid in Kern, CA · In queue since June 2012 · Proposed COD April 2014

170 MW

Capacity

1

Components

Solar

13y 9m

In Queue

Suspended

IA Status

COD target: 2014

Interconnection Timeline

Total Duration

1y 10m

Suspended38%
Queue EntryJun 12, 2012

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-04-30

Project Details

State

CA

County

Kern

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Rosamond 230kV Switching Station

Data Source

LBNL