170 MW hybrid in Kern, CA · In queue since June 2012 · Proposed COD April 2014
170 MW
Capacity
1
Components
Solar
13y 9m
In Queue
Suspended
IA Status
COD target: 2014
Interconnection Timeline
Total Duration
1y 10m
Suspended38%
Queue EntryJun 12, 2012
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2014-04-30
Project Details
State
CA
County
Kern
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Rosamond 230kV Switching Station
Data Source
LBNL
No news available for this project.