BetaActiveSolarBatteryLADWPLBNL
500 MW hybrid in Clark, NV · In queue since June 2024 · Proposed COD June 2026
500 MW
Capacity
2
Components
Solar + Battery
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2 years
In Study38%
Queue EntryJun 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-30
Technology
Solar250 MW · 50%
Battery250 MW · 50%
Project Details
State
NV
County
Clark
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Marketplace 500kV Switching Station
Data Source
LBNL
No news available for this project.