BetaActiveBatteryLADWPLBNL
100 MW storage in Los Angeles, CA · In queue since June 2024 · Proposed COD July 2027
100 MW
Capacity
1
Components
Battery
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 1m
In Study38%
Queue EntryJun 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
CA
County
Los Angeles
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
River 230kV Switching Station
Data Source
LBNL
No news available for this project.