BetaActiveSolarLADWPLBNL
300 MW generation in San Bernardino, CA · In queue since March 2008 · Proposed COD December 2023
300 MW
Capacity
1
Components
Solar
18 years
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
15y 9m
Schedule
27 months past proposed COD
Construction75%
Queue EntryMar 12, 2008
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2023-12-29
Project Details
State
CA
County
San Bernardino
Region
West
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Point of Interconnection
Marketplace-Adelanto 500kV Line
Data Source
LBNL
No news available for this project.