— Project Summary

Queue ID
LADWP-Q03
Capacity
250 MW
Technology
Solar
Status
active
Location
Kern, CA
Region
West
Developer
IA Status
Construction

BetaActiveSolarLADWPLBNL

250 MW generation in Kern, CA · In queue since September 2007 · Proposed COD May 2014

250 MW

Capacity

1

Components

Solar

18y 6m

In Queue

Construction

IA Status

COD target: 2014

Interconnection Timeline

Total Duration

6y 8m

Schedule

145 months past proposed COD

In Study38%
Queue EntrySep 10, 2007

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-05-01

Project Details

State

CA

County

Kern

Region

West

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Point of Interconnection

Barren Ridge 230 kV Sw Station

Data Source

LBNL

No news available for this project.