BetaActiveSolarBatteryJEALBNL
74.9 MW hybrid in Duval, FL · In queue since May 2024 · Proposed COD September 2027
74.9 MW
Capacity
1
Components
Solar
1y 10m
In Queue
Feasibility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 4m
Feasibility Study13%
Queue EntryMay 9, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-30
Project Details
State
FL
County
Duval
Region
Southeast
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Point of Interconnection
Peterson
Data Source
LBNL
No news available for this project.