BetaActiveSolarBatteryJEALBNL
74.9 MW hybrid in Duval, FL · In queue since July 2021 · Proposed COD January 2024
74.9 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 6m
Schedule
27 months past proposed COD
In Study38%
Queue EntryJul 7, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-01-15
Project Details
State
FL
County
Duval
Region
Southeast
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Point of Interconnection
Brandy Branch Sub
Data Source
LBNL