BetaActiveGasJEALBNL
645 MW generation in Duval, FL · In queue since February 2018 · Proposed COD May 2023
645 MW
Capacity
1
Components
Gas
8y 1m
In Queue
Feasibility Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
5y 3m
Schedule
35 months past proposed COD
Feasibility Study13%
Queue EntryFeb 22, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-01
Project Details
State
FL
County
Duval
Region
Southeast
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Point of Interconnection
Greenland Energy Center
Data Source
LBNL
No news available for this project.