BetaActiveSolarJEALBNL
50 MW generation in Duval, FL · In queue since December 2017 · Proposed COD December 2020
50 MW
Capacity
1
Components
Solar
8y 3m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3 years
Schedule
64 months past proposed COD
Construction75%
Queue EntryDec 21, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2020-12-31
Project Details
State
FL
County
Duval
Region
Southeast
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Point of Interconnection
Dinsmore Sub
Data Source
LBNL
No news available for this project.