50 MW generation in Duval, FL · In queue since December 2017 · Proposed COD December 2020
50 MW
Capacity
1
Components
Solar
8y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3 years
Suspended38%
Queue EntryDec 21, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2020-12-31
Project Details
State
FL
County
Duval
Region
Southeast
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Point of Interconnection
Westlake Sub
Data Source
LBNL
No news available for this project.