— Project Summary

Queue ID
JEA-JEA-Q003-PV
Capacity
50 MW
Technology
Solar
Status
suspended
Location
Duval, FL
Region
Southeast
Developer
IA Status
In Progress (unknown study)

BetaSuspendedSolarJEALBNL

50 MW generation in Duval, FL · In queue since December 2017 · Proposed COD December 2019

50 MW

Capacity

1

Components

Solar

8y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2019

Interconnection Timeline

Total Duration

2 years

Suspended38%
Queue EntryDec 21, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-12-31

Project Details

State

FL

County

Duval

Region

Southeast

Developer

Utility

Jacksonville Electric Authority

Entity

JEA

Point of Interconnection

Cecil Commerce North Sub

Data Source

LBNL

No news available for this project.