Bay State Wind 4 Offshore Wind
BetaActiveOffshore WindISO-NELBNL + Live
1,200 MW generation in MA · In queue since December 2019 · Proposed COD November 2033
1,200 MW
Capacity
1
Components
Offshore Wind
6y 3m
In Queue
IA Executed
IA Status
COD target: 2033
Interconnection Timeline
Total Duration
13y 11m
Construction75%
Queue EntryDec 18, 2019
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 36–60 months
Commercial Operation
Proposed COD: 2033-11-04
Project Details
State
MA
County
—
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
National Grid Brayton Point 345kV
Data Source
LBNL + Live