FPS Panton Solar — Project Summary

Queue ID
ISO-NE-807
Capacity
50 MW
Technology
Solar
Status
active
Location
Addison, VT
Region
ISO-NE
Developer
IA Status
IA Executed

FPS Panton Solar

BetaActiveSolarISO-NELBNL + Live

50 MW generation in Addison, VT · In queue since December 2018 · Proposed COD May 2026

50 MW

Capacity

1

Components

Solar

7y 3m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 5m

Construction75%
Queue EntryDec 13, 2018

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-05-31

Project Details

State

VT

County

Addison

Region

ISO-NE

Developer

Utility

ISO-NE

Entity

ISO-NE

Point of Interconnection

Vergennes 115 kV Substation

Data Source

LBNL + Live

No news available for this project.