Revoultion Offshore wind
BetaActiveOffshore WindISO-NELBNL + Live
704 MW generation in RI · In queue since September 2018 · Proposed COD September 2025
704 MW
Capacity
1
Components
Offshore Wind
7y 6m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
7 years
Schedule
7 months past proposed COD
Construction75%
Queue EntrySep 13, 2018
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 36–60 months
Commercial Operation
Proposed COD: 2025-09-07
Project Details
State
RI
County
—
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
NG 115 kV Davisville substation, Washington County
Data Source
LBNL + Live