Park City Offshore Wind
BetaActiveOffshore WindISO-NELBNL + Live
791 MW generation in MA · In queue since December 2017 · Proposed COD December 2029
791 MW
Capacity
1
Components
Offshore Wind
8y 3m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
12 years
Construction75%
Queue EntryDec 15, 2017
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 36–60 months
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
MA
County
—
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
Eversource 345 kV West Barnstable Substation
Data Source
LBNL + Live
No news available for this project.