Vineyard Offshore Wind — Project Summary

Queue ID
ISO-NE-624
Capacity
800 MW
Technology
Offshore Wind
Status
active
Location
MA
Region
ISO-NE
Developer
IA Status
IA Executed

Vineyard Offshore Wind

BetaActiveOffshore WindISO-NELBNL + Live

800 MW generation in MA · In queue since November 2016 · Proposed COD May 2025

800 MW

Capacity

1

Components

Offshore Wind

9y 4m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

8y 6m

Schedule

10 months past proposed COD

Construction75%
Queue EntryNov 8, 2016

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 36–60 months

Commercial Operation

Proposed COD: 2025-05-26

Project Details

State

MA

County

Region

ISO-NE

Developer

Utility

ISO-NE

Entity

ISO-NE

Point of Interconnection

115 kV Barnstable Substation