Battery Storage — Project Summary

Queue ID
ISO-NE-1555
Capacity
214.156799 MW
Technology
Battery
Status
active
Location
Essex, MA
Region
ISO-NE
Developer
IA Status
System Impact Study

Battery Storage

BetaActiveBatteryISO-NELBNL + Live

214.157 MW storage in Essex, MA · In queue since June 2024 · Proposed COD January 2028

214.157 MW

Capacity

1

Components

Battery

1y 9m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

3y 7m

Impact Study25%
Queue EntryJun 6, 2024

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-01

Project Details

State

MA

County

Essex

Region

ISO-NE

Developer

Utility

Entity

ISO-NE

Point of Interconnection

115KV Line Q-169 between Resco-Saugus Tap and Melrose #2 Tap. Approximately 2.4 miles from Melrose #2 Tap and approximately 2.35 miles from Resco-Saugus Tap

Data Source

LBNL + Live