Battery Storage — Project Summary

Queue ID
ISO-NE-1546
Capacity
202.070007 MW
Technology
Battery
Status
active
Location
Berkshire, MA
Region
ISO-NE
Developer
IA Status
Feasibility Study

Battery Storage

BetaActiveBatteryISO-NELBNL + Live

202.07 MW storage in Berkshire, MA · In queue since May 2024 · Proposed COD June 2030

202.07 MW

Capacity

1

Components

Battery

1y 10m

In Queue

Feasibility Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

6y 1m

Feasibility Study13%
Queue EntryMay 30, 2024

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-06-06

Project Details

State

MA

County

Berkshire

Region

ISO-NE

Developer

Utility

Entity

ISO-NE

Point of Interconnection

MA_WMECO Partridge 115kV substation.