Battery Storage — Project Summary

Queue ID
ISO-NE-1543
Capacity
588.299988 MW
Technology
Battery
Status
active
Location
Barnstable, MA
Region
ISO-NE
Developer
IA Status
Feasibility Study

Battery Storage

BetaActiveBatteryISO-NELBNL + Live

588.3 MW storage in Barnstable, MA · In queue since May 2024 · Proposed COD December 2028

588.3 MW

Capacity

1

Components

Battery

1y 10m

In Queue

Feasibility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 7m

Feasibility Study13%
Queue EntryMay 28, 2024

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

MA

County

Barnstable

Region

ISO-NE

Developer

Utility

Entity

ISO-NE

Point of Interconnection

The project will tap the Bourne-Jordan Pond (342) 345kV line with a new three breaker ring bus to connect the project.

Data Source

LBNL + Live

No news available for this project.