Battery Storage
BetaActiveBatteryISO-NELBNL + Live
588.3 MW storage in Barnstable, MA · In queue since May 2024 · Proposed COD December 2028
588.3 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Feasibility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
4y 7m
Feasibility Study13%
Queue EntryMay 28, 2024
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
MA
County
Barnstable
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
The project will tap the Bourne-Jordan Pond (342) 345kV line with a new three breaker ring bus to connect the project.
Data Source
LBNL + Live
No news available for this project.