Battery Storage
BetaActiveBatteryISO-NELBNL + Live
202.07 MW storage in Hampden, MA · In queue since May 2024 · Proposed COD January 2030
202.07 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Feasibility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
5y 8m
Feasibility Study13%
Queue EntryMay 28, 2024
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-01-24
Project Details
State
MA
County
Hampden
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
MA_WMECO Blandford 115kV substation
Data Source
LBNL + Live
No news available for this project.