Battery Storage — Project Summary

Queue ID
ISO-NE-1515
Capacity
508.399994 MW
Technology
Battery
Status
active
Location
Berkshire, MA
Region
ISO-NE
Developer
IA Status
Feasibility Study

Battery Storage

BetaActiveBatteryISO-NELBNL + Live

508.4 MW storage in Berkshire, MA · In queue since April 2024 · Proposed COD August 2028

508.4 MW

Capacity

1

Components

Battery

1y 11m

In Queue

Feasibility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

4y 4m

Feasibility Study13%
Queue EntryApr 9, 2024

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-08-30

Project Details

State

MA

County

Berkshire

Region

ISO-NE

Developer

Utility

Entity

ISO-NE

Point of Interconnection

Alps-Berkshire 345kV line

Data Source

LBNL + Live