Battery Storage
19.3 MW storage in Franklin, VT · In queue since March 2024 · Proposed COD July 2026
19.3 MW
Capacity
1
Components
Battery
2 years
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-01
State
VT
County
Franklin
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
Direct connection to VELCO 115kV Highgate substation (44.943833, -73.058515)
Data Source
LBNL + Live
PJM awards interconnection agreements to 23 BESS resources
PJM has awarded 23 battery energy storage system (BESS) resources, totalling 2.2GW, with interconnection agreements (IAs) in its first...
Texas company eyes former Vermont Yankee site for battery energy storage system
Representatives from PowerTransitions have been meeting with officials in Vernon about potentially developing the 140-acre site along the...
Texas company eyes former Vermont Yankee site for battery energy storage system
Representatives from PowerTransitions have been meeting with officials in Vernon about potentially developing the 140-acre site along the...
Vermont Electric and Green Mountain Power launch new large-scale battery in North Troy
A new battery storage project in North Troy seen on Friday, August 16. Photo by Glenn Russell/VTDigger. NORTH TROY — Operators cut...
Last updated 2026-03-26