Battery Storage
19.3 MW storage in Windsor, VT · In queue since February 2024 · Proposed COD July 2026
19.3 MW
Capacity
1
Components
Battery
2y 1m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-01
State
VT
County
Windsor
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
Direct connection to VELCO 115kV Windsor substation (43.48988, -72.40858)
Data Source
LBNL + Live
PJM awards interconnection agreements to 23 BESS resources
PJM has awarded 23 battery energy storage system (BESS) resources, totalling 2.2GW, with interconnection agreements (IAs) in its first...
Texas company eyes former Vermont Yankee site for battery energy storage system
Representatives from PowerTransitions have been meeting with officials in Vernon about potentially developing the 140-acre site along the...
Texas company eyes former Vermont Yankee site for battery energy storage system
Representatives from PowerTransitions have been meeting with officials in Vernon about potentially developing the 140-acre site along the...
Green Mountain Power seeks to install up to 1,200 storage batteries in remote homes
The state's largest electric utility is asking state regulators to approve a new tariff for all its ratepayers that would fund a project to...
Last updated 2026-03-26