Solar — Project Summary

Queue ID
ISO-NE-1428
Capacity
101.549004 MW
Technology
Solar
Status
active
Location
Rockingham, NH
Region
ISO-NE
Developer
IA Status
System Impact Study

Solar

BetaActiveSolarISO-NELBNL + Live

101.549 MW generation in Rockingham, NH · In queue since July 2023 · Proposed COD December 2025

101.549 MW

Capacity

1

Components

Solar

2y 8m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 5m

Schedule

3 months past proposed COD

Impact Study25%
Queue EntryJul 25, 2023

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-30

Project Details

State

NH

County

Rockingham

Region

ISO-NE

Developer

Utility

Entity

ISO-NE

Point of Interconnection

A tap at existing 115 kV line between Eversource 115kV Scobie Pond - Pulpit Rock Line A184 115kV. * The new tap will be located at approx. 42.9292184N, -71.2567898W and along a ~6 mile segment of Line A184 (approx. 4.9 miles northeast of Scobie Pond and approx. 1.1 miles southwest of Pulpit Rock).

Data Source

LBNL + Live