Solar
25 MW generation in Hartford, CT · In queue since April 2022 · Proposed COD November 2025
25 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
State
CT
County
Hartford
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
To interconnect at the POI of Gravel Pit Solar QP 1030, via a Shared Facility, QP 1030 is described as a line cut and three-breaker ring bus of the 115 kV Connecticut Light & Power Company line between Barbour Hill and Windsor Locks.
Data Source
LBNL + Live
CT Siting Council approves solar expansion in East Windsor
The project would add 150 acres to the existing Gravel Pit Solar facility, increasing output by 30 megawatts. Some residents were dismayed.
Solar farm one step closer to expanding in East Windsor
The developers of a solar farm in East Windsor are looking to expand, and they could be one step closer to doing so.
Community solar projects continue to grow in CT. The aim is to bring down rising energy costs
Connecticut's Shared Clean Energy Facilities Program allows residents to reap the benefits of solar who are not eligible to install solar...
Greenskies wraps up 3.13-MW community solar project in Connecticut
Greenskies Clean Focus announced it has completed a 3.13-MWDC solar project in Durham, Connecticut. Spanning 10 acres and featuring more...
Last updated 2026-03-26