Solar — Project Summary

Queue ID
ISO-NE-1247
Capacity
25 MW
Technology
Solar
Status
active
Location
Hartford, CT
Region
ISO-NE
Developer
IA Status
In Progress (unknown study)

Solar

BetaActiveSolarISO-NELBNL + Live

25 MW generation in Hartford, CT · In queue since April 2022 · Proposed COD November 2025

25 MW

Capacity

1

Components

Solar

3y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 7m

Schedule

5 months past proposed COD

In Study38%
Queue EntryApr 5, 2022

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-11-01

Project Details

State

CT

County

Hartford

Region

ISO-NE

Developer

Utility

ISO-NE

Entity

ISO-NE

Point of Interconnection

To interconnect at the POI of Gravel Pit Solar QP 1030, via a Shared Facility, QP 1030 is described as a line cut and three-breaker ring bus of the 115 kV Connecticut Light & Power Company line between Barbour Hill and Windsor Locks.

Data Source

LBNL + Live