Solar
150 MW generation in Hartford, CT · In queue since March 2022 · Proposed COD November 2028
150 MW
Capacity
1
Components
Solar
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
State
CT
County
Hartford
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
345kV Line 3419 Tap between Meekville Junction/Barbour Hill (PSSE Bus Number: 119103) To LudlowPSSE Bus Number: 116045)
Data Source
LBNL + Live
Ellington To Consider Resolution Opposing Solar On Farmland
The proposal comes after the state approved the Gravel Pit Solar expansion in neighboring East Windsor.
Solar farm one step closer to expanding in East Windsor
The developers of a solar farm in East Windsor are looking to expand, and they could be one step closer to doing so.
Community solar projects continue to grow in CT. The aim is to bring down rising energy costs
Connecticut's Shared Clean Energy Facilities Program allows residents to reap the benefits of solar who are not eligible to install solar...
Greenskies wraps up 3.13-MW community solar project in Connecticut
Greenskies Clean Focus announced it has completed a 3.13-MWDC solar project in Durham, Connecticut. Spanning 10 acres and featuring more...
Last updated 2026-03-26