Battery Storage
301.26 MW storage in Norfolk, MA · In queue since March 2022 · Proposed COD November 2026
301.26 MW
Capacity
1
Components
Battery
4 years
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-23
State
MA
County
Norfolk
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
Primary: West Medway 345kV station
Data Source
LBNL + Live
Battery storage moves forward in Massachusetts as barriers fall
Development and construction of battery energy storage systems (BESS) in Massachusetts has become more feasible as a result of expanded...
Flatiron Energy Closes on $540M for Battery Energy Storage Project Largest in Massachusetts
Flatiron Energy has reached financial close on $540 million to support the Taft Project, a 200 MW battery energy storage facility to be...
Last updated 2026-03-26