Grissom Solar — Project Summary

Queue ID
ISO-NE-1226
Capacity
4.99 MW
Technology
Solar
Status
active
Location
Sullivan, NH
Region
ISO-NE
Developer
IA Status
IA Executed

Grissom Solar

BetaActiveSolarISO-NELBNL + Live

4.99 MW generation in Sullivan, NH · In queue since March 2022 · Proposed COD May 2025

4.99 MW

Capacity

1

Components

Solar

4 years

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 2m

Schedule

11 months past proposed COD

Construction75%
Queue EntryMar 4, 2022

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-05-15

Project Details

State

NH

County

Sullivan

Region

ISO-NE

Developer

Utility

ISO-NE

Entity

ISO-NE

Point of Interconnection

46 kV subtransmission line between GMP Maple Avenue B-42 and the 4402 breaker at the GMP/NGRID demarc considered at Bellows Falls

Data Source