Solar — Project Summary

Queue ID
ISO-NE-1192
Capacity
101.127998 MW
Technology
Solar
Status
active
Location
Hartford, CT
Region
ISO-NE
Developer
IA Status
In Progress (unknown study)

Solar

BetaActiveSolarISO-NELBNL + Live

101.128 MW generation in Hartford, CT · In queue since November 2021 · Proposed COD October 2027

101.128 MW

Capacity

1

Components

Solar

4y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 11m

In Study38%
Queue EntryNov 4, 2021

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-15

Project Details

State

CT

County

Hartford

Region

ISO-NE

Developer

Utility

ISO-NE

Entity

ISO-NE

Point of Interconnection

N. Bloomfield to Agawam 345kV Line. POI is approximately 3.6 mi north of N. Bloomfield (345kV) and 11.5 mi south of Agawam (345kV).