Solar Knox
BetaActiveSolarISO-NELBNL + Live
33.5 MW generation in Knox, ME · In queue since October 2021 · Proposed COD March 2027
33.5 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 5m
Construction75%
Queue EntryOct 28, 2021
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-03-31
Project Details
State
ME
County
Knox
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
CMP 115kV Line 80
Data Source
LBNL + Live