Twin Energy Wind
BetaActiveWindISO-NELBNL + Live
18.3 MW generation in Oxford, ME · In queue since October 2021 · Proposed COD October 2025
18.3 MW
Capacity
1
Components
Wind
4y 5m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4 years
Schedule
5 months past proposed COD
Construction75%
Queue EntryOct 25, 2021
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-10-17
Project Details
State
ME
County
Oxford
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
Roxbury Substation
Data Source
LBNL + Live
No news available for this project.