Roxbury Solar
BetaActiveSolarISO-NELBNL + Live
1.999 MW generation in Oxford, ME · In queue since October 2021 · Proposed COD February 2025
1.999 MW
Capacity
1
Components
Solar
4y 5m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 4m
Schedule
14 months past proposed COD
Construction75%
Queue EntryOct 22, 2021
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-02-07
Project Details
State
ME
County
Oxford
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
CMP 12.47 kV distribution circuit 447D1 out of CMP Rumford Substation
Data Source
LBNL + Live
No news available for this project.