Battery Storage
205 MW storage in Washington, RI · In queue since September 2021 · Proposed COD June 2026
205 MW
Capacity
1
Components
Battery
4y 6m
In Queue
Not Started
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
State
RI
County
Washington
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
RIE L190-2 (0.615 miles from Davisville and 1.935 miles from Old Baptist substations).
Data Source
LBNL + Live
Proposed Expansion of Algonquin Natural Gas Pipeline in R.I. Raises Hackles of Residents, Environmental Advocates
Enbridge, the company that owns the Algonquin natural gas pipeline that runs through sections of R.I., is proposing an expansion of the...
Proposed Expansion of Algonquin Natural Gas Pipeline in R.I. Raises Hackles of Residents, Environmental Advocates
Enbridge, the company that owns the Algonquin natural gas pipeline that runs through sections of R.I., is proposing an expansion of the...
Proposed Expansion of Algonquin Natural Gas Pipeline in R.I. Raises Hackles of Residents, Environmental Advocates
Enbridge, the company that owns the Algonquin natural gas pipeline that runs through sections of R.I., is proposing an expansion of the...
Proposed Expansion of Algonquin Natural Gas Pipeline in R.I. Raises Hackles of Residents, Environmental Advocates
Enbridge, the company that owns the Algonquin natural gas pipeline that runs through sections of R.I., is proposing an expansion of the...
Last updated 2026-03-26