Battery addition
BetaActiveHydroBatteryISO-NELBNL + Live
6.7 MW hybrid in Franklin, MA · In queue since August 2021 · Proposed COD August 2025
6.7 MW
Capacity
1
Components
Hydro
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
4 years
Schedule
7 months past proposed COD
In Study38%
Queue EntryAug 6, 2021
Interconnection request submitted to ISO/RTO
TCS StudyCurrent
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-08-17
Project Details
State
MA
County
Franklin
Region
ISO-NE
Developer
—
Utility
—
Entity
ISO-NE
Point of Interconnection
National Grid's PTF (E-5B, F-6 West PTF transmission lines)
Data Source
LBNL + Live
No news available for this project.