Husky Solar — Project Summary

Queue ID
ISO-NE-1138
Capacity
50.159 MW
Technology
Solar
Status
active
Location
Windham, CT
Region
ISO-NE
Developer
IA Status
IA Executed

Husky Solar

BetaActiveSolarISO-NELBNL + Live

50.159 MW generation in Windham, CT · In queue since June 2021 · Proposed COD May 2028

50.159 MW

Capacity

1

Components

Solar

4y 9m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 11m

Construction75%
Queue EntryJun 3, 2021

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-05-10

Project Details

State

CT

County

Windham

Region

ISO-NE

Developer

Utility

ISO-NE

Entity

ISO-NE

Point of Interconnection

The POI will be located about 6.9 miles from the 1607/1505 line ROW (Exeter Tap) and about 1.1 miles from the Exeter Sub 54N along the 115 kV underground line to the Exeter Sub 54N.

Data Source

LBNL + Live