Husky Solar
50.159 MW generation in Windham, CT · In queue since June 2021 · Proposed COD May 2028
50.159 MW
Capacity
1
Components
Solar
4y 9m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-10
State
CT
County
Windham
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
The POI will be located about 6.9 miles from the 1607/1505 line ROW (Exeter Tap) and about 1.1 miles from the Exeter Sub 54N along the 115 kV underground line to the Exeter Sub 54N.
Data Source
LBNL + Live