Nutes Solar
BetaActiveSolarISO-NELBNL + Live
20 MW generation in Strafford, NH · In queue since May 2021 · Proposed COD May 2026
20 MW
Capacity
1
Components
Solar
4y 10m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5 years
Construction75%
Queue EntryMay 20, 2021
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-05-15
Project Details
State
NH
County
Strafford
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
4323'7.50"N, 71 1'23.45"W, Direct Tap, Circuit #3174 34.5 kV
Data Source
LBNL + Live
No news available for this project.