Green Apple Solar
BetaActiveSolarISO-NELBNL + Live
178.59 MW generation in Androscoggin, ME · In queue since February 2021 · Proposed COD November 2027
178.59 MW
Capacity
1
Components
Solar
5y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 9m
Construction75%
Queue EntryFeb 15, 2021
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-11-01
Project Details
State
ME
County
Androscoggin
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
44.172365, -70.104225 CMP 115kv Line 212
Data Source
LBNL + Live
No news available for this project.