SolarFairfield
BetaActiveSolarISO-NELBNL + Live
18.14 MW generation in Somerset, ME · In queue since December 2020 · Proposed COD June 2027
18.14 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
6y 6m
Construction75%
Queue EntryDec 17, 2020
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-06-30
Project Details
State
ME
County
Somerset
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
New Rice Rips 34.5 kV Substation in Oakland Maine
Data Source
LBNL + Live
No news available for this project.