Warren Meadow Solar
BetaActiveSolarISO-NELBNL + Live
74.5 MW generation in Knox, ME · In queue since November 2020 · Proposed COD November 2026
74.5 MW
Capacity
1
Components
Solar
5y 4m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6 years
Construction75%
Queue EntryNov 30, 2020
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-11-30
Project Details
State
ME
County
Knox
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
CMP 115kV line Section 80
Data Source
LBNL + Live
No news available for this project.