Emery Meadow Solar
BetaActiveSolarISO-NELBNL + Live
16.425 MW generation in York, ME · In queue since April 2020 · Proposed COD September 2026
16.425 MW
Capacity
1
Components
Solar
5y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 5m
Construction75%
Queue EntryApr 27, 2020
Interconnection request submitted to ISO/RTO
TCS Study
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
ME
County
York
Region
ISO-NE
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Point of Interconnection
CMP 34.5 kV, Section 182
Data Source
LBNL + Live
No news available for this project.