— Project Summary

Queue ID
IP-hist_q17
Capacity
15 MW
Technology
Other
Status
suspended
Location
Gem, ID
Region
West
Developer
IA Status

BetaSuspendedOtherIPLBNL

15 MW generation in Gem, ID

15 MW

Capacity

1

Components

Other

In Queue

IA Status

Interconnection Timeline
Suspended0%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

ID

County

Gem

Region

West

Developer

Utility

Idaho Power Company

Entity

IP

Point of Interconnection

undefined

Data Source

LBNL