4.2 MW generation in Malheur, OR · In queue since August 2024 · Proposed COD March 2025
4.2 MW
Capacity
1
Components
Solar
1y 7m
In Queue
IA Executed
IA Status
Signed Dec 1999
Interconnection Timeline
IA → COD
25y 3m
Total Duration
1y 7m
Schedule
13 months past proposed COD
Construction75%
Queue EntryAug 22, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementDec 31, 1999
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-03-01
Project Details
State
OR
County
Malheur
Region
West
Developer
—
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
MRBT41
Data Source
LBNL
No news available for this project.