BetaActiveBatteryIPLBNL
20 MW storage in Ada, ID · In queue since June 2024 · Proposed COD June 2026
20 MW
Capacity
1
Components
Battery
1y 9m
In Queue
IA Executed
IA Status
Signed Dec 1999
Interconnection Timeline
IA → COD
26y 6m
Total Duration
1y 9m
Construction75%
Queue EntryJun 7, 2024
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementDec 31, 1999
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
ID
County
Ada
Region
West
Developer
—
Utility
Idaho Power Company
Entity
IP
Point of Interconnection
Canyon Creek 34.5kV Bus
Data Source
LBNL